Force Majeure Clause Coverage Analysis After Global Disruptions

Outdated force majeure clauses leave companies exposed to modern, overlapping disruptions.

· 9 min read
Cover illustration for “Force Majeure Clause Coverage Analysis After Global Disruptions”
Contract Risk · October 22, 2026 · 9 min read · 2,103 words

Force majeure clause coverage analysis after global disruptions reveals a structural problem. Legacy clauses often leave organizations exposed when disruption makes performance slower, costlier or only partly possible. Closing that gap requires a calibrated clause architecture, supported by active contract management.

Why force majeure clauses written for a stable world fail under compounding disruptions

The Strait of Hormuz crisis brought the mismatch into focus at scale. Iran's effective closure of the strait since 28 February 2026 stranded nearly 2,000 ships, disrupting the movement of materials on which commercial commitments depended. For affected organizations, the immediate contractual question was whether those commitments were excused, delayed or still enforceable. A clause drafted around an isolated event and a return to normal could not necessarily distinguish those outcomes.

Disruptions since 2020 have shown this weakness time and again. Pandemics, container shortages, port congestion, cyberattacks, tariffs, export controls, sanctions and sustained climate-related disruptions have tested contracts built for discrete, recoverable shocks. These events can overlap, so the end of one does not necessarily restore performance. Yet many templates still draw a clear line between business as usual and an exceptional interruption. The world's risk profile has changed faster than the language used to allocate it.

How courts interpret force majeure clauses, and why that makes the drafting problem worse

Common law courts in the US and UK generally read force majeure clauses narrowly and rely on what the text says, without adding protection the parties left out. Coverage depends on whether the event is expressly listed or clearly captured, whether it caused the failure to perform and whether the affected party mitigated. Baker McKenzie's April 2026 EMEA guidance identifies the causal link between the event and actual inability to perform as the greatest source of dispute. A commercial burden is not necessarily a legal inability.

Under ejusdem generis, “any other cause beyond the party's reasonable control” can be limited to events similar to those expressly listed. A list of natural disasters therefore may not extend to a pandemic or sanctions regime. In COVID litigation, clauses that expressly named epidemic, pandemic or quarantine generally gave stronger coverage than generic catch-alls. In civil law jurisdictions, force majeure is also partly set out in statute, though the contract's wording still governs what it covers.

Foreseeability creates a further trap as disruptions become familiar. Pandemics after 2020, European conflict supply-chain disruption after the 2022 invasion of Ukraine, and a Hormuz closure after March 2026 may be treated as foreseeable when new agreements are signed. Contracts can address that risk by stating that listed events qualify whether or not foreseeable at contracting. Without that language, the event that prompts a template update may also become harder to invoke. Tariffs make this tension particularly acute because they combine policy foreseeability with economic harm.

The four structural gaps that modern disruptions have exposed in standard force majeure language

The first gap is an event list that does not match the commercial relationship. Boilerplate that covers acts of God, war, strikes and government action may fail to cover transport closures, logistics failures and cyberattacks, or leave their coverage unclear. During the Hormuz crisis, GCC construction projects faced shortages of steel, aluminium and prefabricated components from East Asia, while most supply-chain contracts for those materials had not enumerated a strait closure. The remedy is a relationship-specific list that reflects actual routes, infrastructure, industry dependencies and geographic risks.

The second gap is the exclusion of economic hardship. Force majeure generally addresses inability to perform. Tariff shocks exposed the consequence for suppliers and buyers bound to contracts whose economics had fundamentally changed but whose obligations remained enforceable. The remedy is to separate force majeure from hardship provisions, with defined triggers for tariff increases, freight cost surges and currency devaluations. That separation creates a renegotiation path without treating every cost increase as an excuse for non-performance.

The third gap is the absence of express mitigation duties. A clause may suspend obligations without specifying what the affected party must do to restore performance. That omission leaves questions about alternative supply, rerouting and partial performance to legal defaults that vary by jurisdiction. Modern clauses should require reasonable steps to limit disruption and return to full performance as soon as practicable. They should also define reasonable steps for the particular obligation.

The fourth gap is binary relief for graduated disruption. A delivery may be impossible, delayed or achievable only at materially higher cost, yet a legacy clause may offer only full suspension or termination. Those facts belong under different contractual regimes. The remedy is to distinguish impossibility, delay or hindrance, increased cost, government action and stoppage instructions, then specify the relief each permits.

Why the Strait of Hormuz crisis is the stress test legacy clauses were never designed to pass

The Hormuz crisis tested more than the wording of a war or government-action trigger. Insurance premiums for vessels transiting the affected waters quadrupled, Brent crude surged sharply, and landed costs of imported construction materials in Saudi Arabia rose substantially since late February 2026. Those effects did not present the same performance problem for every agreement. A blocked shipment raised a different claim from a delivery that remained possible at greater expense. The initiating event alone could not determine the appropriate remedy.

The disruption also crossed transport systems. EUROCONTROL reported that air traffic between Europe and the Middle East dropped steeply on 28 February and 1 March 2026 and remained significantly depressed year-on-year into the week of 9–15 March. Airspace closures therefore compounded shipping disruption rather than providing a separate, neatly bounded shock.

A coverage analysis must therefore look at how the geopolitical event affects the obligation at issue. It must distinguish actual prevention from delay or additional cost, then examine the required mitigation and available relief. Contracts entered into or renewed after the crisis began face the additional argument that closure was reasonably foreseeable. The longer a disruption becomes part of the known trading environment, the less protection an unqualified appeal to exceptional circumstances may provide.

Why tariff shocks and regulatory change require contractual mechanisms force majeure was never designed to provide

Treating tariffs as foreseeable policy risk is legally well-grounded. Courts have long been reluctant to accept economic hardship, market fluctuations and government policy shifts as reasons to excuse performance. The answer is not to force tariffs into a doctrine designed for a different problem. It is to give their commercial effects a contractual home before a cost shock becomes a breach dispute.

Baker McKenzie's EMEA guidance recommends targeted mechanisms for tariffs and regulatory change because force majeure is a limited safety net. Price-adjustment formulas and defined tariff thresholds can allocate cost changes without requiring proof of impossibility. Delivery terms can state who pays customs-related costs and who is responsible for customs matters. Bespoke sanctions provisions serve a different purpose by capturing newly imposed measures that prohibit or materially impede performance. Forum-selection and governing-law provisions then shape where and under which rules disputes will be resolved.

Regulatory adjustment also extends beyond trade costs. The EU's Digital Operational Resilience Act, effective January 17, 2025, changed requirements for financial entities' third-party contracts and ICT operational resilience. The European Commission's Data Act model contractual terms, published November 2025, set out how to structure data access and cloud computing agreements outside the force majeure framework. These developments call for contract adjustment. Cross-border agreements therefore need an architecture that separates physical impossibility, economic unsustainability, regulatory prohibition, cost shocks and changes in law.

What a future-proof force majeure clause architecture looks like in practice

The first layer is a precise triggering-event list tailored to the relationship. It should enumerate relevant natural events, public health emergencies, cyberattacks, infrastructure failures, transport closures and industry-specific supply-chain disruptions. Government responses, including quarantine orders, shutdown orders and export controls, should be addressed distinctly from the events that prompt them. The clause should expressly state whether listed events qualify regardless of foreseeability at contracting.

The second layer is graduated relief tied to the nature and severity of disruption. Delay can justify a time extension, while partial suspension can preserve payment for completed work. Increased burden can be addressed through cost reimbursement, and sustained disruption through renegotiation rights. Termination should follow defined prolonged non-performance rather than operate as the only alternative to continued performance. Long-term supply and infrastructure contracts should specify when alternative routes, sources or methods remain required and what cost threshold triggers relief.

The third layer is a separate hardship clause with objective economic triggers. The contract should establish the tariff rate, freight index or currency rate at signing and define the change that activates relief. It should then specify whether that change leads to renegotiation, cost-sharing or termination rights. Baker McKenzie's guidance supports hardship provisions to deal with a major change in the commercial balance without automatically excusing non-performance. A stated baseline makes that distinction workable.

The fourth layer has provisions tailored to sanctions, export-control and regulatory-change risks. Sanctions language should capture both measures in place at signing and newly imposed measures. Change-in-law clauses should address regulatory shifts requiring operational adjustment or renegotiation. Delivery terms should allocate customs-related costs, while governing-law and forum-selection provisions should reflect the regulatory environment in which disputes may arise.

The fifth layer is an express set of notice and mitigation duties. The affected party should give notice within a defined window, take specified reasonable steps to limit disruption, partially perform where possible and resume full performance as soon as practicable. These duties connect entitlement to relief with conduct during the disruption. Baker McKenzie identifies the drafting tension between detailed lists that may exclude unlisted events and broad formulations that are difficult to apply. Drafting requires calibrated specificity.

How contract management infrastructure determines whether well-drafted clauses actually work under pressure

When disruption occurs, organizations must find the affected agreements, check notice deadlines, work out their mitigation duties and find the remedies they can use. Fragmented repositories, email threads and static PDFs make that work difficult within contractual timeframes. A valid underlying claim can fail if notice is late or cannot be documented.

Version-controlled clause libraries and approval workflows translate drafting standards into consistent agreement language. AI-assisted review can then help extract force majeure provisions, surface obligation schedules and flag notice requirements across large portfolios. Its usefulness does not remove the need for governance. Hallucinations remain a documented risk in legal RAG pipelines, so organizations should assess system design, training and output verification before relying on AI-generated analysis in a live dispute.

Docusign's Intelligent Agreement Management platform helps meet these needs through Agreement Manager, CLM and AI-powered tools including Iris. Its capabilities support centralized repositories, version-controlled clause libraries, automated notice and obligation workflows, and extraction of actionable agreement intelligence at scale. These functions connect the agreed allocation of risk to the steps required when that risk materializes. The operational value lies in making contractual rights and duties accessible while there is still time to act.

The resulting record also matters in enforcement. Electronic execution with immutable timestamps, IP capture and device records helps build a trail of evidence for amendments, notices and side letters tied to a disruption. For execution to be legally binding under ESIGN and eIDAS, it must meet the rules that apply under each framework, including consent, intent and the appropriate signature tier under eIDAS. Execution records support the documentation needed to establish what was agreed and when. That audit trail returns the operational argument to the courts' scrutiny of timing, causation and conduct.

The coverage analysis as a standing practice, not a one-time response to the current crisis

Coverage analysis should be a standing governance practice rather than a response reserved for the next emergency. Updating templates in response to a disruption deals with what just happened but leaves the next kind of risk unresolved. Periodic review should test event lists against current exposures, identify what has become foreseeable and recalibrate hardship thresholds. Jurisdiction-by-jurisdiction analysis should examine how governing law interacts with the intended allocation of risk.

That review must also reach the agreements already in use. Version control and approval workflows should carry revised language into active templates, while AI-assisted portfolio screening can identify legacy clauses for prioritized renegotiation or amendment. These updates should reduce the distance between the organization's actual exposure and the protection its contracts provide.

An outdated force majeure clause is not a neutral omission but an unallocated liability that becomes visible under pressure. A calibrated architecture addresses that liability only when teams can maintain it, find it and act on it. Regular coverage analysis makes those duties part of the routine work of managing agreements. It treats agreements as strategic assets that require active management to support operational resilience.